Paris 2024 generated an economic impact of €7.1bn in Île de France, according to the ex post study EY produced for the French Ministry of Sports, against a comparable CDES forecast of €7.5bn for preparation and staging. Organisation matched the forecast, construction was slightly lower and tourism about 16% lower. Public spending, the organiser’s accounts and the social cost benefit balance are separate questions.
Picture a gallery at the Louvre in early August 2024, quieter than a usual summer, while a few kilometres away the Seine is lined with temporary stands. Both scenes belong to the same economic story, and Paris is one of the few hosts that lets us read it with numbers on both sides: a forecast published before the Games and an ex post study published after them.
My conclusion first. On the same scope and the same period, Paris 2024 landed close to its central regional forecast: €7.1bn measured against €7.5bn expected [1][2]. Organisation spending matched the forecast almost exactly, construction came in a little lower, and tourism was about 16% below. The total is a fair result. It does not answer whether hosting was a good use of public money, and it does not yet tell us much about legacy. Those questions need separate accounts, and Paris now has most of them.

What exactly is being compared?
The forecast is the 2024 update of the ex ante study by the Centre de Droit et d’Economie du Sport (CDES). Its intermediate scenario covers 17 years and totals €8,990m, but €1,460m of that, about 16%, belongs to a legacy phase from 2025 to 2034 [2]. The ex post study, produced by EY for the French Ministry of Sports and dated April 2025, measures only preparation and staging [1]. So the like for like forecast is €7,530m, not €8,990m. Setting €7.1bn against the full range of €6.7bn to €11.1bn would compare a short measurement with a long projection, and the gap would mean nothing.
Forecast and measured economic impact
Scope: Île de France, excluding the 2025 to 2034 legacy phase. Rounded to €0.1bn.
| Estimate | Excluding legacy | Including legacy |
|---|---|---|
| CDES low | 6,184 | 6,707 |
| CDES intermediate | 7,530 | 8,990 |
| CDES high | 9,299 | 11,145 |
| EY ex post | Published as €7.1bn | Not measured |
Both figures are model estimates built on reported inputs. EY combined real spending data, a survey of 113,379 ticket holders and an input output model for indirect and induced effects, with a regional multiplier of 1.26 [1]. That makes the result far more grounded than a forecast, but it is still an estimate of economic activity, not a count of money in a bank account.
Component by component
The headline hides the most useful part of the comparison. When I line up the three components on the same basis, Île de France, direct plus indirect and induced, legacy excluded, the picture is uneven [1][2].
Forecast and result, component by component
Scope: Île de France, direct plus indirect and induced, preparation and staging only, legacy excluded. Light bars: forecast. Solid bars: ex post.
| Component | Forecast (CDES intermediate) | Ex post (EY) | Difference |
|---|---|---|---|
| Organisation | 3.55 | 3.53 | About 0% |
| Construction | 2.43 | 2.28 | About 6% lower |
| Tourism | 1.56 | 1.30 | About 16% lower |
| Total | 7.53 | 7.1 (published) | About 6% lower |
Organisation, meaning the spending of the organising committee and its partners, came in at €3.53bn against a forecast of €3.55bn. Construction was €2.28bn against €2.43bn. Tourism was €1.30bn against €1.56bn. Two of three components were close; the third, the one that depends most on visitor behaviour, missed by roughly a sixth. A close total can conceal a material difference in one part of the event economy, and for a destination manager, that part is usually the one that matters most.
What made up the €7.1bn
Scope: Île de France, ex post. Direct components in solid bars, indirect and induced in light.
| Component | Impact |
|---|---|
| Direct: organisation | 2.8 |
| Direct: construction | 1.8 |
| Direct: tourism | 1.1 |
| Direct total | 5.7 |
| Indirect and induced | 1.3 |
| Total | 7.1 |
| Jobs supported (FTE) | 46,432 |
| Multiplier | 1.26 |
Two notes on reading the result. CDES published its scenarios in current euros, while EY’s visitor comparisons use constant euros, so small differences carry little weight. And this is a test of a forecast updated a few months before the Games, not of every promise made during the bid.
The boundary changes the answer
EY also estimates an impact of about €3bn for France as a whole [1]. A national figure less than half the regional one looks odd until you look at what moves across the boundary.
| Component | Île de France | France | Why it differs |
|---|---|---|---|
| Organisation | 3.53 | About 1.4 | Spending funded from elsewhere in France counts as new money only for the region |
| Construction | 2.28 | About 0 (neutral) | 99% of spending went to French firms, so nationally it mostly shifted activity |
| Tourism | 1.30 | About 1.6 | The national scope also counts visitor spending outside Île de France |
| Total | 7.1 | About 3.0 | Different boundaries; not to be subtracted |
Construction is the clearest case. In Île de France it added €2.28bn, because money arrived from national budgets and firms elsewhere. At national level EY treats it as neutral, since 99% of construction spending went to French companies and mostly shifted activity between French actors [1]. Tourism runs the other way: the national tourism figure is slightly higher than the regional one. The national scope covers visitor spending across France, including at venues outside the capital region, while spending by French visitors from other regions counts as new money only for Île de France. Subtracting one from the other would not show a loss elsewhere; it would mix two methods.
Employment needs the same care. EY reports 46,432 full time equivalent jobs in Île de France, expressed on a one year basis [1]. That is a volume of work, not 46,432 people and not 46,432 permanent posts. EY does add one useful distribution detail: 68% of construction spending went to firms based in Île de France, and small and medium enterprises took more than a third of service and subcontracting contracts [1].
Four accounts, not one return on investment
The most common mistake I see in event debates is folding four different questions into one number. Paris now has an answer to each, from four different bodies, and each answer has its own scope.
| Account | Question it answers | Paris figure | Source |
|---|---|---|---|
| Organising committee (COJOP) | Did the organiser balance its books? | Surplus of €75.7M on revenue of €4,494.2M, which includes €224.1M of public subsidies | Cour des comptes, September 2025 |
| Public spending | What did the state and local authorities spend? | €3.02bn on organisation and €3.63bn on infrastructure | Cour des comptes, September 2025 |
| Economic impact | How much extra activity did the Games generate? | €7.1bn in Île de France; about €3bn in France | EY for the Ministry of Sports, April 2025 |
| Social cost benefit | Did society gain more than it spent? | Net socioeconomic cost under €3bn on prudent assumptions; about €1.5bn on less prudent ones | CRÉDOC for the Haut commissariat au Plan, December 2025 |
The organising committee closed its accounts in June 2025 with a surplus of €75.7m, on revenue of €4,494.2m and spending of €4,418.5m. That revenue included €224.1m of public subsidies [3]. The Cour des comptes, the national audit court, counted €3.02bn of public spending on organisation and €3.63bn on infrastructure, a scope that includes legacy and public participation spending [3]. It put the effect on national GDP at about 0.07 point. A surplus and billions in public spending belong to different ledgers.
The fourth account asks a welfare question. In December 2025 the Haut commissariat à la Stratégie et au Plan published a cost benefit analysis carried out by CRÉDOC. Against public spending of about €6.6bn, it estimated a net socioeconomic cost of under €3bn on prudent assumptions, and about €1.5bn on less prudent ones [4][8]. It also said no conclusion was possible yet on legacy, because many benefits had not been measured or would appear only over time [4]. These are conditional estimates, not an accounting loss, and not a verdict. They do show why an impact total alone cannot justify a bid.
What the tourism figures measure
The tourism shortfall is where Paris teaches most. Foreign spectators who travelled specifically for the Games spent €148 per person per day, tickets and travel to France excluded. In constant euros including VAT, that is €35 less than at the Rugby World Cup 2023 and €47 less than at Euro 2016 [1]. They also had little free time: on average 3.9 days in their stay without attending an event, against 7.6 days for Rugby World Cup visitors [1].
Meanwhile Île de France hotels recorded 23.2 million nights from June to September 2024, 2.2 million fewer than in the same months of 2023, and EY records a 14% fall in Louvre attendance during the Games [1]. EY defines crowding out narrowly, as visitors who could not find accommodation, and on that definition found none [1]. Visitors who simply chose not to come, or moved their trip, are a separate question.
The year on year drop is a warning signal, not a causal estimate, since travellers switch accommodation type or dates. The CRÉDOC analysis shows why distribution matters: it put the 2024 balance for hotels at about minus €10m, while owners of tourist rentals in Île de France gained about €60m [4][8]. A single tourism score would hide that difference.
The visitor’s time budget
The practical finding is about hours, not euros. A spectator who spends the morning in transit, the afternoon in a venue and the evening in queues and security has little room left for the city. More tickets do not automatically mean more visits to museums, markets or neighbourhood restaurants.
In my reading, the spectator day is a shared planning object for the organiser and the destination team. A realistic day includes travel, screening and queues, and short walking routes, cultural opening hours aligned with sessions and onward travel information all shape it. Visits and spending outside venues, and the neighbourhoods reached, are the measures that would show the effect.
Recreation begins with everyday access
Legacy is what residents can use when the visitors have gone. Three public swimming sites opened on the Seine in summer 2025, after more than €1.4bn of investment in water quality [6]. The City of Paris dates the swimming plan to 2015, so the fair question is how much the Games accelerated a longer programme, not whether they did it alone.

The OECD notes that the Olympic Aquatics Centre in Saint Denis opened to the public from mid 2025 for school sessions and leisure swimming, in a department where one in two children cannot swim on entering middle school [7]. It also records that only about 9% of metro stations were accessible, and that around 240 stations and stops were made accessible for the Games, backed by a €1.5bn accessibility fund and 1,000 accessible taxis [7].

Opening a facility proves an asset exists; its public value depends on who uses it, how often and at what price.
Who benefited and who carried the burden
Residents were broadly positive and also inconvenienced, and both are true. In September 2024, 86% of French respondents judged the Games a good thing, while 41% of French people and 38% of Île de France residents said the Games had caused disruption for residents, according to INJEP data cited by CRÉDOC [8]. Those are perceptions, not measured household losses. Volunteers are part of this account too: about 42,000 served with the organising committee, plus more than 5,200 with local authorities [3].
On the environment, the official carbon assessment puts Paris 2024 at 2.085 million tonnes of CO₂ equivalent, or 0.52 tonnes per visitor against 0.9 at the Rugby World Cup 2023 [5]. Two thirds came from visitor travel, and 46% from the 10% of visitors who came from outside Europe. The study credits the use of 95% existing or temporary venues for most of the gain against London 2012, and it explicitly excludes biodiversity [5]. That supports a carbon claim, not a full environmental verdict.
Indicators to track
The Paris evidence points to a short list of indicators, each with a named owner and a publication date. A forecast that separates organisation, construction and tourism lets the ex post study test each one. A visitor study that covers the whole season and every accommodation type gives the full count. A public account that separates operating costs from assets that stay in use keeps the two readable. Legacy monitoring that starts the day a facility opens produces results well before the end of a ten year forecast.
| Indicator | What it shows | When to publish |
|---|---|---|
| Impact by component | Whether organisation, construction and tourism each met the forecast | Ex ante and 12 months after |
| Visitor time budget | Free days per stay and spending outside venues | Visitor survey during the event |
| Whole season accommodation | Nights in hotels and rentals, against a counterfactual | Monthly, for the full season |
| Public cost by ledger | Operating costs separated from assets that stay in use | Audit within 12 months |
| Facility use | Public sessions, prices, school use, disabled access, repeat visits | Yearly from opening |
| Resident burden | Travel time changes and access to public space, by district | During and after the event |
| Employment | Local hires, skills and retention, beyond FTE totals | 12 and 36 months after |
| Environment | Carbon with stated boundary, plus water, waste and biodiversity | Within 12 months |
Analysis result
On the sources used, Paris 2024 met its economic forecast on the same scope: €7.1bn of activity in Île de France against a comparable €7.5bn, with organisation on target, construction close and tourism about 16% lower [1][2]. Public spending of about €6.6bn and a net socioeconomic cost estimated at under €3bn on prudent assumptions show that the impact figure is not a return on public money [4][8]. Residents were broadly positive and also reported disruption [8], and the carbon footprint per visitor was lower than at recent comparable events [5]. The balanced conclusion is that Paris ran a well forecast event whose activity was real and whose public cost was higher than its measured welfare gain, and that the case for hosting now rests on legacy: the Seine swimming sites, the Saint Denis pool and accessible transport. Those are the figures to watch over the next decade.
Frequently asked questions
Who produced the Paris 2024 economic impact studies? The ex ante forecast came from the Centre de Droit et d’Economie du Sport (CDES), updated in April 2024. The ex post study was carried out by EY for the French Ministry of Sports and published in April 2025 [1][2].
Why is the national impact lower than the regional one? The national figure of about €3bn uses a different boundary. Construction is neutral nationally because it mostly shifted activity between French firms, while it counts as new money for Île de France [1].
Did Paris 2024 make a profit? The organising committee closed with a surplus of €75.7m, including €224.1m of public subsidies. Public spending on organisation and infrastructure was about €6.6bn, and a cost benefit analysis estimated a net socioeconomic cost of under €3bn [3][4].
How many jobs did Paris 2024 support? EY reports 46,432 full time equivalent jobs in Île de France on a one year basis. That is a volume of work, not a headcount of permanent jobs [1].
Sources
- EY for the French Ministry of Sports, ex post economic impact study of Paris 2024, April 2025 (PDF)
- CDES, Paris 2024 ex ante economic impact study, updated April 2024 (PDF)
- Cour des comptes, Les Jeux olympiques et paralympiques de Paris 2024, report, September 2025 (PDF)
- Haut commissariat à la Stratégie et au Plan, Jeux de Paris 2024: au delà des coûts budgétaires, quels bénéfices, 16 December 2025
- Ministère de la Transition écologique and EY, ex post carbon assessment of Paris 2024, 2025 (PDF)
- Ville de Paris, Se baigner dans la Seine en 2024 et au delà